The Innovation Call for Proposals (InnAusV) represents another funding instrument for the energy transition in Germany. The legislator introduced it to specifically support innovative approaches in the field of renewable energy beyond the classic EEG funding system. Organised by the Federal Network Agency, the procedure takes place twice a year – on May 1st and September 1st – and is primarily aimed at so-called plant combinations that are still in the planning phase.
Table of Contents
TogglePromotion of large PV systems incl. storage
Accordingly, all technical solutions that consist of combinations of EE systems with storage devices are particularly encouraged through the innovation calls. This also applies to PV systems in conjunction with battery storage as grid-based energy solutions. These combinations not only contribute to the generation of regenerative electricity but also make an important contribution to grid stability and the balancing of load peaks. Unlike the regular EEG calls, the focus here is less on the lowest price but on the added value of the projects for stabilizing the public electricity networks. For operators of large PV systems with storage, the innovation call thus offers attractive funding opportunities and at the same time the opportunity to actively contribute to the flexibility of the electricity system.
Legal basis of an innovation tender
The legal basis for the innovation tenders essentially derives from the Renewable Energy Act and the Innovation Tender Regulation (InnAusV). Particularly relevant are § 39n of the EEG Act, which sets out the basic principles of the tender and the possibility to promote innovative combination of installations.
In addition to this, the InnAusV specifies the details of the tender procedure. It regulates, among other things, the requirements for eligible systems, the design of the innovation bonuses, the deadlines and formal requirements for submitting bids, and the criteria for awarding subsidies.
Compared to regular EEG tenders, the innovation tender allows certain deviations in order to specifically promote technological developments and system-beneficial solutions. The InnAusV thus forms a specialized set of rules for implementing the objectives defined in Section 39n EEG and serves as a legal framework for the practical implementation of the procedures by the Federal Network Agency.
Project requirements for innovation tenders
For innovation tenders from the German Federal Network Agency, plant combinations must meet the following central requirements:
- Composition: It must be a combination of several systems using different renewable energies or a combination of renewable energy and storage. At least one system must use onshore wind energy or solar radiation energy (photovoltaics).
- Common grid connection point: All subsystems must feed into the grid via a common grid connection point.
- Minimum performance: The entire system combination must have an output of at least 1,001 kilowatts. There is no minimum size for individual sub-systems.
- Storage requirements: Storage systems may only store electricity from the other subsystems. The storage capacity must be designed in such a way that the storage system can store electricity that can be fully fed out within two hours. The total capacity of the storage system must correspond to at least 25 % of the total capacity of the system combination
- New plants: All subsystems must not have been put into operation by the bid date.
- Registration: All subsystems must be registered as projects in the market master data register before the bidding date.
- Network serviceability: The system combination must generally be suitable for providing positive secondary control power or supporting other grid services (e.g. absorbing peak loads).
- No double funding: The systems must not already be subsidized by other EEG subsidy programs.
Minimum technical requirements for PV systems & storage systems
In order to meet the minimum requirements for participation in an innovation tender, the overall system must have a capacity of at least 1,001 kW. In practice, for example, a PV system of around 750 kW and a 251 kW storage system with a capacity of at least 500 kW are sufficient. In this case, the storage capacity is 25 % of the total capacity and the storage system can fully feed out the electricity within two hours.
Process of an innovation tender
Five to eight weeks before the deadline for the innovation tender, the tender conditions, the volume, and the maximum value are published. In 2024, for example, the maximum allowable value was 9.18 ct/kWh, and the average surcharge value was 8.33 ct/kWh. For the first tender in 2025, the Federal Network Agency set the maximum value at 9.00 ct/kWh.
Eligible bidders must submit their bids by the deadline and exclusively in written form by post. Electronic submissions are not permitted. After the bid deadline, the Federal Network Agency will check all submissions for correctness of form and content. As a rule, the most economical and grid-compatible projects are awarded contracts, with the most favorable bids being awarded in the event of oversubscription.
After the award, implementation of the project is mandatory within a specified timeframe – usually 30 months. There is a reporting obligation regarding progress and, in the event of non-compliance, sanctions may be imposed. The funding is paid out via a sliding market premium, which is only paid if the market value of the electricity is below the subsidized bid price. In case of negative market electricity prices, the funding payment for the relevant period is not paid.
Advantages of participating in an innovation tender
Participation in an innovation tender offers companies, project developers, and investors several strategic advantages. Unlike traditional EEG tenders, the focus is not solely on the lowest price; rather, the combination of economic viability and system relevance is paramount. Projects that, for example, link photovoltaic systems with storage benefit from more targeted funding and greater acceptance in the tender process.
A special incentive is the sliding market premium: it offers some degree of planning certainty, as it partially offsets fluctuations in the German electricity market. Furthermore, operators of such installations are positioning themselves in a future-oriented manner – as providers of flexible, grid-serving solutions that are gaining importance in an increasingly volatile electricity system. Moreover, successful participation can also send a positive signal to investors, banks, and business partners, as it demonstrates technological expertise and regulatory compliance.
Developments & political classification
The innovation tender is a key instrument of the German federal government to advance the integration of renewable energy sources, in addition to the mere expansion of these sources. By specifically supporting combinations of systems such as photovoltaic power plants and storage systems, the legislator is supporting technical solutions that contribute to grid stability, load shifting, and security of supply. In political and technical circles, the innovation tender is therefore considered an important component of the energy transition – especially in light of the ambitious expansion targets for 2030 and the increasing volatility in the electricity system.
In future, the volume of tenders is expected to increase and the requirements will become more differentiated. Hybrid systems with additional flexibility components such as power-to-heat or intelligent control could also become more of a focus. The political objective is clear: not only more renewable energy, but also more system efficiency. For project developers, this means attractive long-term prospects, but also the need to keep pace in terms of technology and regulation.