From the project to the solar power plant
Light Mobility Solutions – The development process
In Obertshausen, a photovoltaic system with 1,212.72 kWp is being built on 12 hall roofs by Light Mobility Solutions. From the initial inspection to the handover of the roofs to the finished system, this timeline shows how the project is being built step by step.
On this timeline, we document the most important milestones, the construction progress, and the assembly of the central components of the system.
Home " References " Light Mobility Solutions GmbH – Obertshausen
12 roofs, one system
The facility is spread across 12 hall roofs on the factory grounds. The numbering in the image is used throughout the timeline.
Roofs
Module
kWp
kWh per year
August 25th
November 13th
The kick-off for Obertshausen
The project is starting: A photovoltaic system with 1,212.72 kWp is to be installed on 12 roof terraces at Light Mobility Solutions in Obertshausen.