Selected PROJECTS

References: Excerpt of our successful photovoltaic & battery storage projects

Insights into our realized energy projects – from planning to implementation.

Construction processes:

Battery storage in Tušimice

Cube Concepts - 50 MW / 100 MWh

Photovoltaics in Ebern

FTE automotive systems (Valeo) - 3,2 MWp

Photovoltaik in Oldenburg

J. Bünting - 238 kWp

Selected references at a glance:

Over 300 MWp

installed

42.9 million kWh

Solar power per year from the references shown

27,450 t CO2

Savings per year from the references shown

over 200,000 m²

Module area from the references shown

CO₂ calculation: 639.92 g CO₂ per kilowatt hour of solar power according to the German Environment Agency (Umweltbundesamt; emissions balance of renewable energy sources, reference year 2024)

Photovoltaic system on the roof of the Tucker GmbH (aerial view)
Giessen

Tucker GmbH

Model:

CUBE purchase

Solar power system:

1.28 MWp

Square meters:

6.388 m²

Electricity generation:

1,213,650 kWh/year

CO₂ savings:

776.639 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Photovoltaic system at Yanfeng in Neustadt, oblique view
Neustadt

Yanfeng

Model:

CUBE Contracting

Solar power system:

1.18 MWp

Square meters:

5,780 m²

Electricity generation:

1,180,000 kWh/year

CO₂ savings:

755.106 kg/year

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Photovoltaic system on the roof of Krones AG
Neutraubling

Krones AG

Model:

CUBE purchase

Solar power system:

1.08 MWp

Square meters:

5,410 sq m

Electricity generation:

1,027,900 kWh/year

CO₂ savings:

657.774 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park
Hückelhoven

DICO Drinks GmbH

Model:

CUBE purchase

Solar power system:

1.04 MWp

Square meters:

5.187 m²

Electricity generation:

985,530 kWh/year

CO₂ savings:

630.660 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park
Rakovnik

Purem by Eberspächer

Model:

CUBE Contracting

Solar power system:

1 MWp

Square meters:

4,761 m²

Electricity generation:

1,035,000 kWh/year

CO₂ savings:

662.317 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park
Coesfeld

Weiling GmbH

Model:

CUBE purchase

Solar power system:

999 kWp

Square meters:

4.994 m²

Electricity generation:

948,860 kWh/year

CO₂ savings:

607.194 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Metal processing company
Halsbrücke

Metal processing company

Model:

CUBE purchase

Solar power system:

933 kWp

Square meters:

3.840 m²

Electricity generation:

767,200 kWh/year

CO₂ savings:

490.947 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Reference_FK_FinePaper
Trossingen

FK Feinpapier Kompetenz GmbH

Model:

CUBE purchase

Solar power system:

908 kWp

Square meters:

4.541 m²

Electricity generation:

862,771 kWh/year

CO₂ savings:

552.104 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Reference Valeo Bietigheim-Bissingen
Bietigheim-Bissingen

Automotive supplier

Model:

CUBE Contracting

Solar power system:

789 kWp

Square meters:

3,540 m²

Electricity generation:

830,450 kWh/year

CO₂ savings:

531.422 kg/Jahr

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park
Grevenbroich

TST Logistic GmbH

Model:

CUBE purchase

Solar power system:

4.71 MWp

Square meters:

23,553 m²

Electricity generation:

4,475,108 kWh/year

CO₂ savings:

2,863,711 kg/year
Reference_TST_Gernsheim_New
Gernsheim

TST Logistic GmbH - Gernsheim

Model:

CUBE purchase

Solar power system:

3.9 MWp

Square meters:

19,513 m²

Electricity generation:

3,707,518 kWh/year

CO₂ savings:

2,372,515 kg/year
Photovoltaic system on the logistics hall of TST Logistic in Alzey (aerial view)
Alzey

TST Logistic GmbH

Model:

CUBE purchase

Solar power system:

2.74 MWp

Square meters:

13.717 m²

Electricity generation:

2,606,268 kWh/year

CO₂ savings:

1,667,803 kg/year
Photovoltaic system at the Siegenia plant (aerial view)
Wilnsdorf

Siegenia-Aubi KG

Model:

CUBE purchase

Solar power system:

2.41 MWp

Square meters:

12,069 m²

Electricity generation:

2,293,110 kWh/year

CO₂ savings:

1,467,407 kg/year
Open-air photovoltaic system of the SCHÄFER Werke (aerial view)
Neunkirchen

Schäfer Werke GmbH & Co. KG

Model:

CUBE purchase

Solar power system:

2 MWp

Square meters:

9.729 m²

Electricity generation:

2,121,295 kWh/year

CO₂ savings:

1,357,459 kg/year
PV Purem by Eberspeacher
Wilsdruff

Purem by Eberspächer

Model:

CUBE Contracting

Solar power system:

1.9 MWp

Square meters:

9,231 m²

Electricity generation:

1,864,111 kWh/year

CO₂ savings:

1,192,882 kg/year
Reference TI automotive
Heidelberg

TI Automotive GmbH

Model:

CUBE Contracting

Solar power system:

1.89 MWp

Square meters:

9 m²

Electricity generation:

1,896,600 kWh/year

CO₂ savings:

1.213.672 kg/Jahr
Placeholder for reference image: Battery storage container in front of solar park
Neunkirchen

Purem by Eberspächer

Model:

CUBE Contracting

Solar power system:

1.87 MWp

Square meters:

8,347 m²

Electricity generation:

1,973,561 kWh/year

CO₂ savings:

1.262.921 kg/Jahr
Photovoltaic system at the Federal-Mogul plant in Herdorf (aerial view)
Herdorf

Federal-Mogul Sealing Systems GmbH

Model:

Contracting

Solar power system:

1.39 MWp

Square meters:

6.933 m²

Electricity generation:

1,317,289 kWh/year

CO₂ savings:

842.960 kg/Jahr
Construction site of the energy project in Tušimice, Czech Republic (aerial view)

Under construction

Tušimice

Cube Concepts

Model:

Power:

50 MW

Capacity:

100 MWh, first expansion phase

Commissioning planned:

Q1 2027

Amortization:

Fondium Mettmann reference

Under construction

Mettmann

Fondium Group

Model:

–

Power:

40 MW

Capacity:

80 MWh

Commissioning planned:

Q1 2027

Amortization:

–
Placeholder for reference image: Battery storage container in front of solar park
Sing

Fondium Group

Model:

–

Power:

25 MW

Capacity:

43 MWh

Commissioning planned:

Q1 2027

Amortization:

–
Placeholder for reference image: Battery storage container in front of solar park

In planning

Greifswald

ml&s manufacturing, logistics and services GmbH & Co. KG

Model:

CUBE Contracting

Power:

4 MW

Capacity:

8 MWh

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park

In planning

Dresden

Federal-Mogul

Model:

CUBE Contracting

Power:

1 MW

Capacity:

2 MWh

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park

In planning

Bad Düben

Profiroll Technologies GmbH

Model:

Power:

1 MW

Capacity:

2 MWh

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park

Under construction

Zwickau

WP Holding GmbH

Model:

CUBE purchase

Power:

1 MW

Capacity:

2 MWh

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park

In planning

Ebern / Fischbach

FTE automotive systems GmbH

Model:

CUBE Contracting

Power:

750 kW

Capacity:

1500 kWh

Commissioning planned:

Amortization:

Placeholder for reference image: Battery storage container in front of solar park

In planning

Oberboihingen

Thermal Management Solutions DE

Model:

Power:

Capacity:

Commissioning planned:

Amortization:

This is what our customers say:

Marcus Düber
Marcus DüberManaging Director, SCHÄFER WERKE Group
„The completion of the solar park is a crucial step towards a sustainable future. The investment of millions represents a key component of our concept, which aims to achieve our own climate neutrality by 2030 in accordance with Scope 1 and 2.“
Ralf Gabler
Ralf GablerManaging Director, Pfefferkorn & Schneider
„We can use around 450,000 kWh directly in our buildings and also feed approximately 210,000 kWh into the public grid. In this way, we make an important contribution to environmental protection.“
Matthias Ellinger
Matthias EllingerHead of Facility Management, Syntegon Crailsheim
„We have achieved the full CO₂ target for 2022 using the plant, which also benefits the Syntegon 2025 targets.“
Marcel Hergarten
Marcel HergartenManaging Partner, Hergarten
„With the investment in renewable energy, we also made a statement during the pandemic that the important issue of climate protection must not be forgotten despite all the economic turmoil.“
Gunnar Büchter
Gunnar BüchterExecutive Director Procurement & Strategy Europe, Yanfeng
„Thanks to the switch to climate-neutral solar energy production, we can carry out our manufacturing processes more environmentally friendly and resource-efficient.“

Your location as the next reference?

We review your load profile and profitability – free of charge and with no obligation.

Solar carports - aerial view

Newsletter registration