ToggleWhat is an asset summary?
The system summary is a regulatory term from the Renewable Energy Act (EEG). It regulates when several photovoltaic systems that are separate in themselves are treated as a single, larger system for purposes of compensation, system size, and other EEG requirements.
This is highly relevant for operators of large commercial PV systems. The summary determines whether a system falls into a higher performance class, whether there are tendering obligations, and how expansions or repowering affect the remuneration claim. Currently, § 24 EEG 2023 is the relevant legal basis.
The system overview is not a technical, but a legal term. It is not only the spatial proximity or the shared cable routes that are crucial, but above all the location, commissioning date, type of system, and point of connection to the grid.
When are PV systems grouped together?
Several photovoltaic systems are generally treated as a single system if the following conditions are met: at the same time are met:
- Location: The facilities are located on the same property, in the same building, on the same operating premises, or in other ways in immediate spatial proximity.
- Type of facility: They generate electricity from similar renewable energy sources (in the case of photovoltaics, solar power).
- Funding: For the electricity generated, there is a performance-based payment claim under the EEG.
- Start-up period: The facilities will be located within twelve consecutive calendar months put into operation.
In a summary, the commissioning date of the last generator put into operation is decisive. A later addition can therefore move an existing system to a higher power class and trigger additional regulatory requirements.
Office and commercial parks
Basically, PV systems are installed on or near buildings as well as on noise protection walls. not together, when they are over different network connection points feed into the grid. This is particularly relevant for commercial real estate assets: Multiple rooftop PV systems on different buildings can therefore be treated separately, provided that each system has its own Grid connection point has.
However, if multiple systems use the same network connection point, there is a significant risk that the network operator will aggregate them – provided that the other requirements are also met. Therefore, companies should coordinate network connection, metering concept, and billing with the network operator early on.
Ground-mounted systems
For PV off-grid systems or Solar parks stricter aggregation rules apply. Assets are aggregated for the purpose of determining the size of the portfolio if they:
- within in the same municipality lie,
- within the framework of 24 consecutive calendar months be put into operation and
- at most two kilometers in a straight line are spaced apart from one another (the relevant factor is the outer edge of the respective installation).
Here too, the generator that was last in operation is crucial. A seemingly small second plant can therefore make an entire project portfolio appear significantly larger.
Consequences for project developers: Property boundaries, municipal boundaries, commissioning planning, and grid connection must be considered together from the outset. Any subsequent expansion or a neighboring project could otherwise change the regulatory classification of the entire system group.
Impact on remuneration
A common misconception is that a built-in PV system automatically receives the remuneration of the existing system. However, this is not the case.
Under the EEG, basically every solar module is a separate installation with its own commissioning date and its own remuneration rate. The previous remuneration claim for existing modules remains unchanged; however, it is not simply transferred to newly added modules.
The remuneration for an extension is generally determined according to the rules in effect at the time of construction. This also applies if the extension is carried out within the summary period.
| Impact of the summary | |
| System Size | The performance of the combined systems is considered as a total performance. |
| Compensation (Inventory) | The existing modules' current remuneration entitlement remains basically unchanged. |
| Compensation (construction) | New modules receive the set that is relevant for their own commissioning date. |
| Tenders | An addition can raise the overall system above relevant performance limits and thus trigger tendering obligations or opportunities to participate. |
| Grid connection | The network interconnection point, performance, measurement concept, and remote controllability must be planned consistently. |
Planning expansions properly
Expansion is referred to when the installed power of a photovoltaic system increases – whether through additional modules or as part of a repowering project. Before any construction begins, operators, planners, and grid operators should clarify the following points:
- Start-up distance: For roof and operational site PV, the relevant period is twelve months; for off-site systems, 24 months.
- Network connection point: In the case of building-mounted PV, a separate grid connection point can prevent this from happening (to be considered from a network engineering, economic and contractual perspective).
- Performance thresholds: An addition can increase the total output by thresholds such as 100 kWp or 750 kWp, which changes the requirements and tender requirements.
- Registration: Every new installation must be registered in the market data register (MaStR) within one month after commissioning.
- Contracts: Lease, electricity supply, financing contracts and network operator agreements should reflect scenarios for expansion and consolidation.
Repowering of commercial installations
Repowering Describes the exchange of old PV modules for newer, more powerful modules. This is ideal for commercial installations to achieve higher yields on a limited area.
Since Solar package I Is it possible to repower rooftop systems regardless of whether the old modules are defective (previously, the module replacement was more closely linked to damage). The regulatory logic involved:
- The existing remuneration claim can be claimed during a repowering pro rata and for the remaining funding period to be transferred to the new modules.
- If the installed power increases with more modern modules, the Multiple amount paid according to the rules for new installations.
- In the case of open-air facilities, a corresponding repowering regulation has already been in place since 2022.
Repowering is therefore not simply maintenance: if the installed output increases, there is also an expansion, so that both summary and remuneration consequences must be considered.
Outlook: Planned changes to the asset summary
The draft for the EEG 2027 Proposes changes to the regulations regarding the asset summary. Although these have not yet been rendered legally binding, they should already be taken into account in long-term project planning:
- The summary rules are intended to apply in the future also to determining the payment obligation under § 21d as well as to the investment size under §§ 20 to 22.
- Solar systems of the second segment (roofs, noise protection walls, garden PV) will no longer be grouped together with solar systems of the first segment in the future.
- A more differentiated treatment for open spaces is to be introduced under § 35 BauGB (outdoor area) and § 30 BauGB (building plan).
- The current fixed feed-in tariff for small solar installations is to be gradually replaced by mandatory direct marketing or network operator take-over (fixed tariffs for installations under 25 kWp are currently scheduled to remain in place until the end of 2028).
For commercial rooftop installations, the core message remains the same: network connection point and construction date determine the outcome. In the case of open space projects, however, the design increases complexity by providing greater differentiation based on installation type and building code regulations.
FAQ about the asset summary
What does the system summary mean for PV systems?
The system summary results in several separate photovoltaic systems being treated as a single, larger system for subsidy purposes. The decisive factors are the location, the time of commissioning, the type of system, and the point of connection to the grid.
When are commercial PV systems aggregated?
In the case of rooftop and utility-scale PV, the aggregation principle generally applies when the facilities are located close to one another, generate solar electricity, have a performance-based payment claim, and are commissioned within twelve consecutive calendar months.
Do multiple roof-mounted PV systems always count as one system?
No. Rooftop systems are not grouped together when they feed into different grid interconnection points.
What role does the network connection point play?
It is the central planning lever in building PV. Separate grid connection points often prevent aggregation, while a common point significantly increases the risk of aggregation (subject to compliance with the remaining deadlines).
What deadline applies for open-air facilities?
Here, the relevant period is 24 consecutive calendar months. Additionally, the facilities must be located in the same municipality and be at a maximum of two kilometers apart from one another.
Does a new addition automatically receive the remuneration of the existing facility?
No. New modules generally receive the remuneration rate that applies at the time of their own commissioning date. The old remuneration entitlement remains unchanged for the existing fleet.
What happens with an extension?
The installed capacity increases. Whether a summary is conducted depends on the location, time period, type of facility, and connection point. The new capacity is remunerated according to the rules for new installations.
Will the old remuneration remain when repowering is implemented?
The existing remuneration entitlement can be transferred in part and for the remaining funding period. However, any additional benefits (surplus) will be remunerated as a new investment.
Does the system summary apply in the EEG 2027?
The EEG-2027 draft plans various adjustments (including to § 24), but is not yet in effect at present. For existing and planned projects, the framework of the EEG 2023 currently applies for the time being.