Gas power plant tender 2026: Favorable subsidy, expensive bill for consumers?

Low feed-in tariffs do not automatically mean cheap electricity. High CO₂ costs, market concentration, and the exclusion of battery storage raise fundamental questions about the future of energy supply.

Overview

  • Low surcharge rates: The average premium for long-term capacity is €155,296 per real MW per year, which is significantly lower than the maximum price of €244,000.
  • High market concentration: 10 of the 11 wins were secured by the energy companies LEAG (7) and RWE (3).
  • The CO₂ paradox effect: Low construction and bidding costs for simple open-cycle gas turbines (OCGT) mean poorer efficiency (35–40%). At full load, this drastically drives up the CO₂ certification costs and fuel costs.
  • Battery storage is disadvantaged: Large storage facilities were completely excluded from the calculation due to the strict 10-hour requirement under § 12 of the StromVKG.
  • Political sharpening: The Ministry of Economic Affairs is reacting to the start of the second round with a new regulation against premature coal shutdowns.

Discussions following the first gas power plant tender

The first bidding round for long-term capacity under the Electricity Supply Security Act (StromVKG) has sparked considerable discussion in the energy sector. While the Federal Ministry of Economics and Climate Protection and the Federal Network Agency view the low bid values as a success for cost control, industry analysts and environmental organizations are sounding the alarm.

On second glance, the auction results reveal a fundamental problem: the short-term savings from capacity promotion threaten to lead to significantly higher electricity and CO₂ costs for consumers in the long term.

The results of the first StromVKG tender in summary

With a tendered volume of 4,500 real megawatts (rMW), a total of eleven bids were submitted to the Federal Network Agency. All eleven bids were accepted and received the award for a total capacity of 5,160 rMW.

Parameter / Result
Specified performance4,500 rMW
Additional volume5,160 rMW (11 bids)
Maximum permissible bid value244,000 Euro / rMW / year
Average surcharge value155,296 Euro / rMW / year
Estimated funding amount (15 years)about 12 billion euros
Market distributionLEAG (7 allowances), RWE (3 allowances), Stadtwerke Karlsruhe (1 allowance)

The winner's duopoly: How LEAG and RWE dominate the market

A central point of criticism regarding the tender concerns market concentration. Ten of the eleven bids were won by the two large corporations. LEAG and RWE. Only one surcharge went to a municipal utility – the Stadtwerke Karlsruhe with a combined heat and power (CHP) project.

The reasons for this imbalance lie primarily in the stock infrastructure:

  1. Power connection & area: For the new units, LEAG and RWE mainly use existing power plant sites from former coal and gas power plants (e.g., Jänschwalde, Boxberg, Weisweiler).
  2. Cost and time advantage: The conversion or addition of facilities with existing high-voltage and gas grid connections significantly reduces capital costs (CapEx).

Industry associations such as the Association of Municipal Enterprises (VKU) criticize that the lack of maximum volume limits per bidder has inherently disadvantaged smaller market participants and municipal utilities.

The CO₂ dilemma: Built cheaply, expensive to operate

Why is a low surcharge of around €155,000/rMW not an automatic win for the consumer? The key lies in the turbine technology chosen.

  • LEAG primarily focuses on OCGT (Open-Cycle Gas Turbines): These open-cycle gas turbines require less capital investment in construction, which is why LEAG was able to place very low bids in the auction. However, their major disadvantage is their low efficiency of only 35 to 40%.
  • RWE relies on GuD (gas and steam combined systems): These offer a significantly higher efficiency of approximately 60 to 65%, but result in higher initial construction costs.

Why this increases electricity prices

Capacity reserves are specifically used during periods of low feed-in from renewable energy sources (Dark doldrums) The operators of OCGT turbines consume significantly more natural gas per kilowatt-hour of electricity when operating, and therefore emit correspondingly more CO₂.

As the costs of CO₂ certificates in the European Emissions Trading System (EU-ETS) are steadily increasing, the running costs of these power plants are increasing enormously. The savings from the subsidies in the bidding phase thus threaten to be wiped out again through the ongoing wholesale electricity prices.

A short study by the Forum for an Ecologically Sustainable Social Market Economy (FÖS) commissioned by Green Planet Energy already reached similar conclusions in the spring of 2026, as our report “New Study on Gas Power Plants: How Expensive Is Electricity from Natural Gas, Really?”shows.

System error: Why battery storage remained unsuccessful

Another criticism of energy transition experts concerns the exclusion of large-scale storage. In the first round of the electricity VKG, not a single increase for large companies Battery storage.

The reason for this is enshrined in § 12 StromVKG: The legislation requires that subsidized installations must be at least 10 hours continuously They must provide at least 80% of their rated power. Most large battery storage systems currently in operation are designed for a discharge duration of 2 to 4 hours.

Renewable energy associations such as the bne and the BSW-Solar therefore demand that the framework conditions for upcoming bidding rounds be adapted to offer flexible, emission-free storage systems a fair chance.

Quick fix in the fast pace: BMWK tightens rules for the 2nd tender

The massive criticism of the results of the first round has led to direct consequences within the Federal Ministry of Economic Affairs (BMWK) under Minister Katherina Reiche. As early as the start of the second tranche, over 3,840 megawatts (deadline: December 29, 2026), the ministry announced a detailed regulation to prevent any incentives for the conversion of coal-fired power plants.

The three core points of the new regulation:

  1. Protection against premature shutdown: A conversion from coal to natural gas is only considered a eligible new construction project if the coal-fired power plant is already in operation. July 22, 2026 was closed down or according to the Coal Extraction Act No later than January 1st, 2030 This must be turned off to prevent operators from prematurely taking out of service intact coal-fired power plants just to claim state subsidies.
  2. Real new investments instead of mere cosmetic changes: To be eligible for funding, there must be at least one megawatt of measurable output per year. 431,000 euros invested in. The new regulation makes it clear: Only the construction of new power plants or the significant expansion of existing facilities counts. The favorable and simple burner replacement in old boilers will no longer be eligible for participation in the future. Only genuine companies will be allowed to participate in the future. Fuel-Switch power plants.
  3. Protection for the first round: The regulation retroactively applied the surcharges from the first round (including those for LEAG and RWE). no effects. The 5,160 rMW allocated there remain in place, which is why the amount for the second round was reduced from 4,500 to 3,840 megawatts, as planned.

Classification for the electricity price: The tightening of the rules will slow down future entrants, but it will not remedy the fundamental systemic flaws of the first round. Neither does the regulation change anything about the dominance of the large corporations from Tranche 1, nor does it lift the rigid 10-hour delivery obligation for climate-friendly large battery storage systems. This is not due to be lifted until later tranches (e.g., from May 2027).

Outlook

The first tender following the StromVKG shows a clear conflict of objectives: the desire for low capacity costs led to the preference for large fossil-fuel companies and more technically simple but more emission-intensive types of installations.

For the next bidding rounds, policymakers need to readjust. To create a sustainable energy landscape, they need flexibility bonuses for high efficiency levels, fair access opportunities for large-scale storage, and regulations against excessive market concentration.

FAQ on the 2026 gas power plant tender

Why were the surcharge rates so low in the first electricity VKG tender?

The average bid value was 155,296 euros per MW per year – significantly below the legal maximum price of 244,000 euros. The main reason is that bidders like the LEAG primarily rely on open-cycle gas turbines (OCGT) at existing power plant sites. The lower construction and infrastructure costs allowed the companies to submit very low bid values in the auction.

Why does the low bid price still lead to higher electricity costs?

Cheap OCGT turbines have a poor efficiency of only 35 to 40% compared to gas-and-steam combined plants (GuD). Once these power plants are ramped up to cover peak loads, they consume significantly more gas per kilowatt-hour produced and emit more CO₂. The high running costs of CO₂ and fuel directly feed into the electricity wholesale price and increase the operating cost of electricity.

Why did LEAG and RWE receive almost all the subsidies?

Ten of the eleven bids went to LEAG (7) and RWE (3). Both large corporations already have ready-made grid connections and gas network connections at their existing coal and gas power plant sites (e.g., Jänschwalde, Boxberg, Weisweiler). This enormous time and financial advantage almost completely marginalized municipal actors and smaller providers.

Why did battery storage systems not receive a single grant?

The Electricity Supply Security Act (§ 12 StromVKG) links the subsidy to the condition that an installation must provide 80% of its nominal output for at least 10 hours continuously. Since most economically operated large batteries are currently designed for 2 to 4 hours of discharge duration, they were left out of this tender despite their CO₂-free operation and quick controllability.

From practice

More than 300 MWp installed: References with key figures per project

Photovoltaics and battery storage for industry and commerce: performance, power output and CO₂ savings per installation, plus feedback from our customers.

Free initial consultation

Analyze load profile — get a first assessment in 30 minutes.

CUBE CONCEPTS analyzes grid connection, load profile, and price structure — manufacturer-independent, open-book, without commitment.

More interesting articles

Grid-Forming Inverters-2

Grid forming with grid-forming inverters

Grid forming replaces the missing inertia of conventional power plants with software. Grid-forming inverters, in conjunction with storage systems, act as active voltage sources, providing “virtual inertia” and thus enabling grid stability as well as black starts in a purely renewable energy-based system.

Read more "

Search

What are you looking for?

Results starting with 3 characters · Enter all hits · Esc close · Ctrl+K opens the search everywhere

Frequently searched for

Solar carports - aerial view

Newsletter registration