ABOUT THE SOLAR PARK PROJECT

FTE (Valeo) – Process of creation

At the Valeo site in Ebern, a PV open-air installation and a PV rooftop installation are being built. From setting up the construction site to handing over the area and installing the modules on the surface and roof, this timeline shows how the project takes shape step by step.

On this timeline, we document the most important milestones, the construction progress, and the assembly of the central components of the system.

2026

November 16th

Park wired, rooftop system growing

All DC-side work in the park has been completed: the strings have been measured and the construction site has been cleared. The focus now lies on the hall roof. There, the substructure and modules are being assembled, the gratings are being installed, and the string cables are being laid. The mounting brackets for the inverters on the roof have been determined, and lightning protection for the rooftop system is also planned.

2026

October 12

Modules, cable routes and earthing

The modular units are being further assembled and fitted with modules. In parallel, the excavator work in the park is underway: the cable ducts are being laid and stainless steel pipes are being installed between the tables.

2026

October 5th

The first modules are assembled

The frame profiles and substructure continue to grow over the area; the first modules are already installed. In addition, a prototype for the installation of the inverters was built directly on the substructure.

2026

September 25th

Frame profiles and test table

The frame profiles are driven into the ground, creating the base structure for the modular units. A first mock-up table with modules already shows what the finished system will look like.

2026

September 16

The area will be handed over

During a joint inspection with Valeo, the area will officially be handed over for assembly. The conditions are recorded in the protocol: The area is fenced off, mulched and covered with tarpaulins, and the first profile packages for the substructure are ready.

2026

05 September

New fence and surveying

The old fence is removed and the open space is newly fenced off. At the same time, the terrain is surveyed so that the location of the modular tables can be precisely determined.

2026

04 September

The construction site is being set up

Construction machinery and material containers arrive, as well as the first modules, the substructure and the inverters. A stair tower is being built on the building. This marks the start of the construction work.

Search

What are you looking for?

Results starting with 3 characters · Enter all hits · Esc close · Ctrl+K opens the search everywhere

Frequently searched for

Solar carports - aerial view

Newsletter registration