Multi-Use Battery Storage · for Industry from 1 MW

Multi-use battery storage: More cycles ≠ more revenue. It’s the control logic that decides.

Three revenue channels in parallel on the same hardware: FTM marketing on balancing energy and spot markets, BTM optimization against peak loads and grid fees, co-location and self-consumption under MiSpeL (since October 2026). The hardware is multi-use-capable. The control is multi-use-optimized. The difference lies in the EMS, not in the cell.

200,000–300,000 EUR
FTM gross / MW / year
FCR + aFRR + mFRR + Arbitrage
2–4 years
Typical payback
BESS purchase · CUBE CONCEPTS benchmark
~250 €/kWh
CAPEX up to 2 MWh
From 5 MWh: 175–200 €/kWh
January 1st, 2027
Section 118: investment cut-off date
According to the AgNes draft · commissioning by 4.8.2029

01 – Real-world modeling

320,100 € cash flow in the “AgNes price-led” scenario – 1.5 years payback. Status quo: 97,200 €.

CUBE CONCEPTS modeling at a real industrial site in Saxony. 1 MW / 2 MWh BESS, 1,895 kWp existing PV, 6,795 MWh annual consumption, peak load 1,284 kW, grid fee bill ~310k €/year. Modeling in three regulatory configurations based on real half-hourly load data.

Status quo (StromNEV 2026)

97.200 €

Total Annual Cash Flow

of which CUBE 75 %72.900 €
of which customer 25 %24.300 €
Payback5.3 yrs
Project IRR17,2 %
NPV€328k

AgNes scenario, grid-driven

226.500 €

Total Annual Cash Flow

of which CUBE 75 %169.875 €
of which customer 25 %56.625 €
Payback2.2 yrs
Project IRR58,6 %
NPV€1.66M
The lever

AgNes scenario, price-driven

320.100 €

Total Annual Cash Flow

of which CUBE 75 %240.075 €
of which customer 25 %80.025 €
Payback1.5 yrs
Project IRR94,0 %
NPV€2.70 million

The regulatory configuration determines the leverage; Multi-Use makes it usable. Factor 3.3 between the lower and upper limit – with identical hardware, identical control, and the same location.

What do the three configurations mean? Status quo (StromNEV 2026): current regulation with §19 atypical grid usage, valid until 31.12.2028. The two AgNes scenarios represent models B (grid-driven: storage follows grid utilization signals) and A (price-driven: storage follows spot market prices) from the BNetzA discussion paper of 24.09.2025. The draft determination of 06.08.2026 instead provides for a capacity price on the ordered capacity, no successor to atypical grid usage, and discounts only for system-supportive flexibility. The scenarios therefore show a range; CUBE CONCEPTS will recalculate them with the final determination (planned for the end of 2026).

Note on existing PV: The modeled site has a 1,895 kWp PV installation – this has an impact on BTM cash flows (self-consumption optimization). Sites without PV continue to achieve FTM cash flows in full. Multi-Use is fully PV-independent – existing PV strengthens the leverage, but is not a prerequisite.

Source reference: CUBE CONCEPTS load profile modeling April 2026 · BNetzA discussion paper 24.09.2025 (Model A/B) · BNetzA key points on storage grid fees 16.01.2026 and feed-in grid fees 17.02.2026 (AgNes, GBK-25-01-1#3) · BNetzA, AgNes draft determination of 06.08.2026 · KPMG AG, Investment Case: Stationary Battery Storage, February 2026 (Assumptions)

03 – Control logic

How does the controller automatically resolve three daily conflicts?

Multi-Use sounds simple. In practice, three conflicts arise daily that must be resolved automatically, without production intervention.

01

FCR Readiness vs. Peak Shaving Capacity

FCR requires a sustained ~50 % SoC – this ties up capacity that is not available for peak shaving. The CUBE EfficiencyUnit prioritizes hourly based on peak load time windows, load forecast, and market price. FCR causes only ~0.3 full cycles/day – low degradation with significant revenue contribution.

02

Arbitrage window vs. § 19 para. 2 sentence 1 peak load time window compliance

Cheap charging periods conflict with the grid operator’s peak load time windows. §19 atypical grid usage requires that the maximum load in the peak load time windows is significantly below the annual maximum load; charging from the grid during these windows jeopardizes this condition. The CUBE EfficiencyUnit knows all peak load time windows and automatically blocks charging. Proof can be exported directly. Deadline: June 30 of the following year.

03

Cycle Threshold: When is a cycle not worth it?

If the price range is smaller than the proportionate cycle costs (degradation + OPEX), the cycle reduces the overall margin. The CUBE EfficiencyUnit calculates the threshold dynamically and executes only profitable cycles. That is the difference between multi-use capable and multi-use optimized.

Multi-use capable vs. Multi-use optimized

Multi-Use Capable
Hardware Claim

The system is technically capable of multiple operating modes. Manual switching. No automatic conflict resolution. Manual update of peak load time windows. FCR and peak shaving are not simultaneously coordinated. §19 compliance depends on operator decisions.

Multi-Use optimized
CUBE EfficiencyUnit

Automatic real-time prioritization of all revenue channels. Peak load time windows updated daily. Cycle threshold calculated dynamically. FCR SoC hold point + peak shaving capacity simultaneously. §19 compliance automatically documented. From 2029: control to the ordered capacity under AgNes on the same platform.

Illustrative Daily Schedule of a Multi-Use Battery Storage System

22:00 – 06:00
Cheap charging

Low market prices. Arbitrage charging. FCR standby at 50 % SoC in parallel.

06:00 – 08:00
Morning ramp

Increasing grid load. Check §19 peak load time windows. Partial discharge for peak shaving readiness.

08:00 – 12:00
Peak Shaving Active

Peak load time window active. Discharge during peak loads. §19 compliance automatically secured.

12:00 – 16:00
PV / Recharging

With PV: self-consumption optimization. Without PV: favorable price windows for recharging.

16:00 – 20:00
Evening peak

Peak shaving + arbitrage discharge. Peak load time window: charging blocked – §19 compliance active.

20:00 – 22:00
FCR / Standby

Balancing energy standby. 50 % SoC. §19 annual documentation in progress.

Illustrative daily schedule – actual control is site-specific and reacts in real time to market and grid signals. The CUBE EfficiencyUnit makes all prioritization decisions fully automatically.

Next step

Control Logic Check: How much is your facility leaving on the table today?

Analyze load profile →

04 – Three Phases & Trajectory

From day-one FTM operation to full multi-use

Multi-Use is not a Big Bang, but a regulated escalation of monetization. Three phases on the same asset – without hardware changes.

01 Phase I – from commissioning

FTM & BTM combined

FTM: FCR + aFRR + mFRR as a supplementary channel + spot market arbitrage via top-tier aggregator. BTM: Peak shaving against demand charges & Section 19 (2) sentence 1 StromNEV (until Dec 31, 2028). Fully automatic, no operational intervention.

→ FTM revenues €200–300k/MW/year + BTM leverage

02 Phase II · MiSpeL since Oct. 2026

PV Co-Location added

With MiSpeL: Hybrid storage (PV + grid) without loss of EEG subsidies under § 19, paragraph 3b of the EEG. PV sites can now combine arbitrage and EEG feed-in for the first time, without the previous either-or situation.

→ Self-consumption + FTM without loss

03 Phase III – starting from AgNes 2029

New grid fee system

The StromNEV expires on December 31, 2028; AgNes replaces it. According to the draft of August 6, 2026, industrial customers pay a capacity price on the ordered capacity; consumption above it costs 2 to 3.5 times the energy charge. Co-location storage systems pay a joint fee with the facility; quantities drawn from the grid and fed back are exempt from the energy charge if metered separately.

→ The storage system keeps consumption below the ordered capacity

Regulatory Trajectory 2025–2029

The regulatory changes from 2025 to 2029 do not act in isolation but as a shift from feed-in to self-consumption. Most levers strengthen multi-use; the end of atypical grid usage in 2028 shifts the BTM lever from the peak load time windows to the ordered capacity.

DateHebelImpact on Multi-Use
since 25.02.2025Solar Peak ActNew PV installations do not receive EEG compensation at negative prices; in 2025 there were 573 hours with negative wholesale prices. PV sites secure their profitability with storage.
18.07.2025Immediate investment programBGBl. 2025 I No. 161: declining-balance depreciation of up to 30 % (§7 para. 2 EStG) for all companies, for acquisitions from 1.7.2025 to 31.12.2027; can be combined with the existing special depreciation under §7g para. 5 EStG (up to 40 %) for prior-year profits up to €200,000.
23.12.2025EnWG and BauGB amendments§11c EnWG: Energy storage systems are in the overriding public interest. §35 para. 1 nos. 11 and 12 BauGB (German Building Code) privilege battery storage systems in the outer zone: in spatial and functional connection with an existing renewable energy plant, or from 4 MW at most 200 m from a substation or a power plant of 50 MW or more. Since December 2025, the §118 exemption also applies to partial feed-back into the grid.
Q1 2026AgNes key pointsBNetzA (GBK-25-01-1#3) has published guidance on storage grid fees (16.01.2026) and feed-in grid fees (17.02.2026).
16.04.2026Industrial electricity priceEU approval (SA.120495). Eligible: sectors in KUEBLL sub-list 1, 91 sectors and subsectors according to the BMWE. Reinvest at least 50 % of the granted amount within 48 months, energy storage explicitly mentioned. 10 % bonus if 80 % of the commitment flows into demand-side flexibility.
29.07.2026EEG Amendment 2027Cabinet decision, BT-Drs. 21/7867: Direct marketing obligation for new installations (gradual), permanent feed-in limit of 50 % for building PV below 100 kW, two-sided contracts for difference from 100 kW. Not yet adopted; planned from 1.1.2027. Self-consumption with storage is gaining in value.
06.08.2026AgNes draft determinationCapacity price on the ordered capacity; no successor to atypical grid usage. New grid-connected storage systems will pay a capacity fee from 2029 (BNetzA estimate 4–7 €/kW per year), no energy charge. §118 exemption for new projects only if the investment decision is made before the determination is announced.
01.10.2026MiSpeL determinationHybrid storage (EEG and grid electricity) without loss of EEG support under § 19, paragraph 3b of the EEG; until 30.09.2027 with the consent of the grid operator and metering point operator.
31.12.2026§118 cut-off date (draft)Last day for the final investment decision to secure the 20-year exemption under §118(6) of the EnWG; announcement of the AgNes determination planned for January 1, 2027.
01.01.2029AgNes launchStromNEV is no longer in effect; the new grid fee system applies. Transitional discounts for existing users until the end of 2031 (draft).
04.08.2029§118 commissioning deadlineLast commissioning date for the 20-year exemption from grid fees on electricity consumption, insofar as electricity is fed back (Section 118(6) of the EnWG).

Source reference: BNetzA, AgNes draft determination of 06.08.2026 · BNetzA key points 16.01.2026 and 17.02.2026 · BNetzA/SMARD, 20.08.2026 · BGBl. 2025 I No. 161 · §11c EnWG · §35 BauGB · BT-Drs. 21/7867 · BMWE, press release 16.04.2026 · BNetzA, MiSpeL determination

05 – Investment Case

How does a gross revenue of 200–300 k€ become an FTM net revenue of 145–245 k€?

Multi-use revenues do not equal gross revenue. Marketing costs and fixed OPEX must be deducted before the net result appears in the investment case.

FTM Gross Proceeds per MW/Year (FCR + aFRR + mFRR + Arbitrage) 200,000–300,000 EUR
− OPEX including marketing (aggregator commission, maintenance, insurance, substation, monitoring) -55 k€
FTM net per MW/year €145,000–245,000

FTM gross revenue 200–300 k€/MW/year and OPEX of around 55 k€/MW/year including marketing: CUBE CONCEPTS’s benchmark figures for multi-use FTM (FCR, aFRR, mFRR, Arbitrage). For comparison: According to the ISEA Battery Revenue Index, the cross-market revenue potential of a 2-hour storage battery was around €259,000/MW in 2025 (2024: around €309,000/MW). Specific revenue depends strongly on location, marketer, and market phase; site-specific modeling is required. Source: ISEA Battery Revenue Index, via pv magazine 23.01.2026.

KPMG comparison calculation – Stationary battery storage

Assumptions of the simplified comparison calculation: 10 MW BESS, 4-hour profile (40 MWh), 2 full cycles per day, 140 €/MWh sale, 30 €/MWh purchase, 10 % marketing costs, WACC 6 % (real), investment 250 €/kWh (LFP), 360 €/kWh (ZnBr), 275 €/kWh (NIB), lifetime 14, 25 and 10 years, respectively. Comparison of the three focus technologies.

10,5 %

IRR LFP

NPV 2,802 kEUR · highest IRR

9,5 %

IRR ZnBr

NPV 5,076 kEUR · highest NPV

110

LCOS LFP €/MWh

Minimum benchmark per cycle

104

LCOS ZnBr €/MWh

Lowest LCOS

Source reference: KPMG AG Wirtschaftsprüfungsgesellschaft, “Investment Case: Stationary Battery Storage”, February 2026 (Figures 5, 7, 9 and 10, pp. 18–21). LFP: NPV 2,802 kEUR, IRR 10.5 %. ZnBr: NPV 5,076 kEUR, IRR 9.5 %. NIB (Sodium-ion battery): NPV 601 kEUR, IRR 7.2 %. Project-related values (unlevered) in a simplified comparison calculation; specific projects may differ significantly.

CAPEX ranges 2026

System SizeConfigurationCAPEX range€/kWh
1 MW2 MWh, 2-hour profile~500.000 €~250 €/kWh
5 megawatts10 MWh, 2-hour profile1.75–2.0 million €175–200 €/kWh
10 MW20 MWh, 2-hour profile€3.5–4.0M175–200 €/kWh

CUBE CONCEPTS benchmark values (project experience 2025/2026), turnkey, indicative. For comparison: the KPMG comparison calculation assumes €250/kWh for LFP (10 MW / 40 MWh).

Immediate investment program – tax levers 2025–2027

For BESS acquisitions between 1.7.2025 and 31.12.2027, the declining-balance depreciation under the Immediate Investment Program applies. It can be combined with the existing special depreciation under §7g EStG, whose scope of application is narrower:

  • 1. Declining-balance depreciation up to 30 % in the first year (§7, paragraph 2 of the EStG) – for all companies regardless of size. Specifically: up to three times the straight-line depreciation, with a maximum of 30% of the acquisition cost per year; in subsequent years, based on the remaining book value.
  • 2. Special depreciation under §7g, paragraph 5 of the EStG up to 40 % spread over up to 5 years – only for businesses with a previous year's profit of up to €200,000 (uniform profit limit since the JStG 2020, §7g, paragraph 6, item 1 of the EStG).

What does that mean for industrial companies? Medium-sized and large industrial companies, typically above the €200,000 profit threshold, use only the declining-balance depreciation (30 % in the first year). The combination giving a 70 % first-year deduction only applies if the business stays within the profit threshold. Individual tax review recommended.

BESS qualifies as a movable fixed asset. Source: Federal Law Gazette (BGBl.) 2025 I No. 161 of 18.07.2025; §7(2) EStG; §7g(5) in conjunction with §7g(6) EStG. This information is provided for information purposes only and does not constitute tax advice. More about the Immediate Investment Program (article on PV systems) →

06 – Site profiles

Which revenue mix is suitable for which location profile?

Multi-use is not a one-size-fits-all strategy. What makes economic sense depends on grid connection, load profile, PV system, and planning horizon.

Location with peak load problem

The demand charge is based on the highest quarter-hour in the billing year: A single peak determines the demand costs for the entire year. Every kilowatt saved at the load peak has immediate, measurable value. BTM comes first – FTM complements.

Location without peak load problems

Free grid connection capacity is the ticket to the balancing energy markets. Without peak load pressure, FTM is immediately the strongest lever. FTM comes first – BTM follows in Phase III.

Profile 1 – Energy-intensive production with peak loads

Primary: Peak Shaving (BTM)

§19 paragraph 2 sentence 1 StromNEV (until 2028) as a lever · FCR additionally from 1 MW system size · Connection mostly medium voltage

Profile 2 – Industry with substantial grid connection

Primary: aFRR + mFRR + Arbitrage (FTM)

200,000–300,000 €/MW/year FTM revenue potential · BTM self-consumption in Phase III – free connection capacity is the entry ticket

Profile 3 – PV site with MiSpeL suitability

Primary: Self-consumption + Peak Shaving (BTM)

Since MiSpeL (October 2026): BTM + FTM combined, hybrid operation without EEG loss according to § 19, paragraph 3b of the EEG

Profile 4 – KUEBLL sector eligible for the industrial electricity price

BESS as industrial electricity price reinvestment

Reinvestment obligation for the industrial electricity price: energy storage units eligible, implementation and financing by third parties permitted, therefore also possible under Contracting

07 – Business models

Buy vs. Contracting – a decision about investment style and distribution of proceeds

Both models are eligible for credit as an investment in energy storage under the industrial electricity price; according to the BAFA, a third party may also finance the measure. What differs is the contractual structure – not the technology.

AspectBESS Contracting (CPFS)BESS Purchase
Customer CapEx0 €Full investment (CAPEX-Backbone)
Customer revenues25% of net market revenues from day 1100% of all revenues and savings
CUBE revenues75% of net market revenues0 %
Balance SheetOff-balance-sheet treatment possible (subject to IFRS 16 assessment)On-Balance
Contract StructureService and Profit Share AgreementSales contract + Maintenance contract
Industrial electricity price reinvestment✓ eligible: implementation by third parties (BAFA guidance note, Chapter 3.5)✓ eligible: own purchase
Hardware ownershipCUBECustomer

Both models are built on the same foundation: manufacturer-independent hardware choice, identical CUBE open-book calculation, identical control phase logic. What differs is the contractual structure – not the technology. Both models count as reinvestment in energy storage under the industrial electricity price.

08 – How Multi-Use Translates into the Business Model

Multi-Use doesn’t start with the storage unit – but with the unused grid connection reserve.

Every industrial site pays for reserved connection capacity – demand charge, basic fee, grid fee. Based on CUBE CONCEPTS’ experience, most sites use only 30–50 % of it. CPFS turns this silent reserve into a revenue stream – without own investment, without hardware risk, with a 25 % profit share for the customer from day 1.

Reserved connection
capacity

Today, 30–50 % are unused

→

Multi-Use BESS

FTM + BTM on one asset

→

Revenue stack

200–300 k€/MW/year gross

Most providers ask “How much can you invest?” or “What is the size of your roof area?”. We ask: How much of your reserved, already paid-for grid connection capacity is unused today? Multi-use storage utilizes exactly this silent reserve without requiring new connection capacity to be applied for. This is a real advantage: In 2025, only 8 % of the connection requests for battery storage were granted in the distribution grid (BNetzA/SMARD).

09 – What sets us apart

Three points that differentiate CUBE CONCEPTS from hardware manufacturers and utility-scale providers

The German BESS market is roughly divided into two camps: hardware manufacturers selling their own technology, and utility-scale providers supplying investment funds. CUBE CONCEPTS is neither.

01
Manufacturer-independent

We run a tender for every project – at least 3 comparative offers. No proprietary system, no manufacturer lock-in. The hardware selection follows the load profile, not the catalog stock.

Hardware manufacturers sell their own technology – that’s their business model.

02
Open Book before contract signing

Full cost transparency before signing: CAPEX, OPEX, profit-share logic, marketing costs. No fixed price without a breakdown. You see what you're buying.

Fixed-price offers without a breakdown are common in the market.

03
0 € CapEx + 25 % Profit Share

CPFS Contracting for C&I customers: no own investment, no hardware risk, 25 % of the net market revenue from day 1 to the customer – CUBE 75 %. Under the industrial electricity price, the storage system counts as a reinvestment, even if CUBE finances it.

Utility-scale providers typically sell to investment funds – not to industrial companies.

Based on 150+ energy projects realized across Europe (PV so far). Industrial electricity price: Directive of 27.04.2026 · BAFA leaflet on decarbonization measures, Chapter 3.5 · CISAF paras. 121–122.

10 – Regulatory levers 2026/2027

Six levers changing multi-use profitability in 2026/2027

Multi-Use is not a natural law, but the result of current regulatory policies. These six levers are the most important – and they do not act in isolation, but as a coordinated shift.

§118 para. 6 EnWG

Exemption for electricity fed back into the grid

20 years of exemption from grid fees on electricity drawn from the grid, insofar as it is fed back; since December 2025 also for partial feed-back. Commissioning by August 4, 2029; according to the AgNes draft, investment decision before January 1, 2027.

Section 19 (2) sentence 1 StromNEV / AgNes

Atypical grid usage privilege → AgNes 2029

Until 31.12.2028: Discount of up to 80 % if the peak load in the peak load time windows is significantly below the annual peak load. From 01.01.2029 according to the AgNes draft: no successor to atypical grid usage, capacity price on the ordered capacity, consumption above it at 2 to 3.5 times the energy charge. Discounts only in return for system-supportive flexibility, e.g. with storage.

MiSpeL since October 2026

Hybrid storage without EEG loss

Market integration of storage systems and charging points: Simultaneous EEG operation and FTM marketing without loss of EEG subsidies under § 19, paragraph 3b of the EEG. PV sites can now combine arbitrage and EEG feed-in for the first time.

EEG Amendment 2027 (government draft)

Direct marketing for new installations

According to BT-Drs. 21/7867: Direct marketing obligation for new installations (phased), permanent feed-in limit of 50 % for building-mounted PV below 100 kW, two-sided contracts for difference from 100 kW. Not yet adopted, planned from 1.1.2027. With storage, more PV electricity can be self-consumed instead of being fed in under the cap.

Industrial electricity price (approved 16.04.2026)

Reinvestment obligation

At least 50 % of the granted amount must be invested within 48 months in measures to reduce the costs of the electricity system; energy storage explicitly mentioned. Eligible: KUEBLL sub-list 1, according to the BMWE, 91 sectors and sub-sectors. A third party may implement and finance the measure; BESS Contracting is thus possible without customer CapEx.

EnWG and BauGB amendments Dec. 2025

§11c EnWG + §35 BauGB

§11c EnWG since 23.12.2025: Energy storage systems are in the overriding public interest and take priority when weighing protected interests. §35, Para. 1 No. 11 BauGB: Battery storage systems spatially and functionally linked to an existing renewable energy installation are privileged in outlying areas, No. 12 covers larger storage systems near substations.

Source reference: §118 para. 6 EnWG · §19 para. 2 StromNEV · BNetzA, AgNes draft determination of 06.08.2026 · BNetzA, MiSpeL determination · BT-Drs. 21/7867 · Industrial electricity price directive of 27.04.2026 · §11c EnWG · §35 BauGB

11 – Who handles the marketing

Multi-use FTM marketing runs through prequalified balancing reserve providers

Only providers that are prequalified with the transmission system operators (Balancing Service Providers, BSP) may supply balancing energy. Industrial storage systems are therefore usually marketed through such a provider, which also trades on the spot market.

Industrial BESS

CUBE EfficiencyUnit control

→

Vertically integrated aggregator

BSP prequalification + trading algorithms

→

Multi-market in parallel

Balancing energy + EPEX Spot

According to the transmission grid operators’ provider list (as of July 8, 2026), 44 companies in Germany are prequalified for balancing reserve. Top-tier aggregators operate their own trading algorithms, are prequalified themselves (rather than going through intermediaries), and market simultaneously in the day-ahead, intraday continuous, and balancing energy markets. This vertical integration determines the revenue difference: Those who have their own software, operate their own data stack, and are directly connected to the transmission grid operators achieve outperformance compared to average market participants.

The CUBE CONCEPTS standard requires a vertically integrated aggregator with BSP prequalification, proprietary trading algorithms, and verifiable multi-market optimization. A pure hardware sales structure without prequalification or proprietary trading software does not achieve this level of depth.

Source reference: Transmission system operators, regelleistung.net: Balancing reserve provider list (as of 08.07.2026) and PQ conditions according to EU guideline SO GL

12 – Safety & Fire Protection

What "multi-use" means in terms of safety

Multi-use increases the cycle frequency, but not the safety requirements – these are technologically independent of the operating mode in stationary LFP storage systems.

Thermal Stability

LFP (Lithium Iron Phosphate) cells are cobalt-free and more thermally stable than other lithium-ion chemistries. Standard for stationary industrial storage.

VdS-certified fire protection concepts

Standardized fire suppression systems, surge protection, and temperature control in enclosed container solutions with a defined IP rating.

Standard-compliant grid integration

VDE-AR-N 4110/4120 (medium/high voltage), IEC 62933-5-2 (safety of battery storage systems), redundant BMS architecture, lightning protection IEC 62305.

The multi-use control system does not affect safety hardware – BMS, fire alarm and extinguishing systems are independent of the operating mode. An FCR system and a multi-use system have the same safety requirements.

13 – Clarification of terms

Multi-Use is not Multi-Market – why the distinction is economically crucial

In the German BESS market, these terms are often used interchangeably. In fact, they describe different revenue models with different economic implications.

Multi-market

FTM Marketing Stack (Front-of-the-Meter)

  • Day-Ahead Trading – Offers for the following day
  • Intraday Continuous – short-term price fluctuations, 5-minute lead time
  • FCR (frequency containment reserve) – ~0.3 full cycles/day
  • aFRR + mFRR – Secondary/Minute Reserve
  • Negative spot prices – Charging arbitrage in surplus hours

Pure FTM optimization – the storage system sits on the public grid, in front of the plant meter.

Multi-Use

FTM + BTM on the same asset

  • All Multi-Market Revenue Streams – FCR, aFRR, mFRR, Spot, Intraday
  • Peak Shaving (BTM) – against the demand charge
  • §19 atypical grid usage / AgNes optimisation – Grid fee reduction
  • Self-consumption optimization – with or without a photovoltaic system
  • UPS / Island operation capability – Security of supply
  • Co-Location with MiSpeL – PV + BESS without EEG loss

Multi-Market PLUS BTM applications on the same system – that is the economic core of Multi-Use.

Multi-Market is therefore a subset of Multi-Use. Anyone operating a pure Multi-Market storage solution leaves the BTM lever unused – peak shaving, §19/AgNes optimization, and self-consumption are not included there. The difference between Multi-Market and Multi-Use is exactly the BTM stack: significant for industrial sites with peak loads, regulatory grid fee leverage, or PV capacity.

14 – Industrial electricity price in 2026

Industrial electricity price: How companies meet the reinvestment obligation with a battery storage system

The EU Commission approved the industrial electricity price on 16 April 2026 (SA.120495). The relief is linked to a reinvestment obligation under the EU aid framework CISAF: At least 50 % of the granted amount must be invested in measures that reduce the costs of the electricity system, energy storage explicitly included.

Eligibility – KUEBLL sub-list 1

Offtake points in Germany in economic sectors with a significant risk of relocation (sub-list 1 of Annex I to the KUEBLL) are eligible; according to the BMWE, these are 91 sectors and sub-sectors with potentially around 9,500 companies, for example from steel, chemicals, aluminum, paper and glass. Other sectors may be added following a decision by the European Commission.

Calculation – 50 % on 50 %

Half of the eligible consumption of an offtake point is subsidized. The difference price is generally 50 % of the reference price (average of the EEX base-load annual futures of the previous year); the remaining price must not fall below the target price of 5 ct/kWh. For 2026: Reference price 8.744 ct/kWh, difference price 3.744 ct/kWh, around 4.1 ct/kWh including the bonus. Billing years 2026 to 2028; application for 2026 retroactively in 2027 to BAFA (deadline March 31, 2027), payment in the following year.

Reinvestment obligation – at least 50 %

At least 50 % of the granted amount must be invested within 48 months (up to 72 if technically justified): in renewable generation (including new PPAs), energy efficiency, demand-side flexibility (including energy storage, electrification, electrolysers, load management) or grid infrastructure. The measures must be located in Germany and may not receive any other aid. The directive explicitly mentions “investments in energy storage”.

Flexibility bonus – +10 %

Applicants who commit, when applying, to investing at least 80 % of their investment obligation in demand-side flexibility receive a bonus of 10 % of the basic aid amount. In addition, 75 % of this bonus must be invested in decarbonization measures. A battery storage system counts as flexibility: As an example, the BAFA cites an electricity storage system that reduces peak loads, optimizes PV self-consumption, or takes advantage of price differences on the spot market.

How Contracting fulfils the obligation

In BESS Contracting, CUBE CONCEPTS bears the full investment. This is permissible: According to the directive and the BAFA guidance note, a third party may implement the measure “not only in material terms but also in financial terms”. The measure does not have to be located at the offtake point applied for, but it must be in Germany. The applicant remains responsible for the implementation and submits the third party’s evidence and declarations of consent. Upon request, the BAFA confirms in advance that a measure is eligible.

Source: Industrial electricity price guideline of 27 April 2026, BAnz AT 06.05.2026 B1, No. 3.1, 4.1, 4.4, 5.1, 5.3 · BAFA Leaflet on Decarbonization Measures, as of 04.08.2026, Chapter 3.4–3.5 · BAFA, industrial electricity price · BMWE, press release 16.04.2026 · EU Commission, CISAF paras. 121–123 · KUEBLL Annex I, sub-list 1

15 – References

150+ energy projects realized across Europe. ~100 MW BESS capacity currently under construction.

Selected industrial companies for whom CUBE CONCEPTS has implemented energy projects in the PV sector so far. Battery storage systems with around 100 MW are currently under construction.

TI Automotive

Magna

Valeo

Voestalpine

Tenneco

ITW

In preparation (2026)

Industrial location Saxony – 1 MW / 2 MWh BESS, 1,895 kWp PV capacity, multi-use modeling in three regulatory configurations

View modeling ↑

Pipeline Project

Thermal Management Solutions DE Oberboihingen GmbH (WAHLER) – BESS Contracting in preparation

PV system in operation since summer 2025. Industrial storage in the Contracting model as the third step of the sustainability strategy. Manufacturer of high-quality thermostat and temperature control technology. Managing Director Holger Kiebel: “Battery storage is the logical next step.”

Read blog post →

16 – Frequently Asked Questions

Multi-Use BESS – Answers for Decision Makers

The twelve most frequently asked questions about multi-use, control logic, economic viability, and regulatory aspects.

The costs per cycle result from investment, degradation, and operation per discharged MWh; the LCOS serves as a benchmark, for LFP €110/MWh in the KPMG comparison calculation (February 2026), with a 2.1 % capacity loss per year. An arbitrage cycle is only worthwhile if the spread exceeds these proportional costs; the CUBE EfficiencyUnit only executes it when the margin is positive. FCR is predominantly paid for availability and only causes around 0.3 cycles per day.

CUBE CONCEPTS estimates a gross revenue potential of €200,000–300,000 per MW per year from FCR, aFRR, mFRR and arbitrage, before around €55,000 in OPEX. According to the ISEA Battery Revenue Index, the cross-market potential of a 2-hour storage system was around €259,000 per MW in 2025, 16 % below 2024. A PV installation is not required for this.

Section 118, paragraph 6 of the EnWG exempts storage systems that go into operation by August 4, 2029 from grid fees on electricity drawn from the grid for 20 years, insofar as the electricity is fed back into the grid. According to the AgNes draft determination of the Federal Network Agency of 06.08.2026, this only applies to new projects if the final investment decision is made before the determination is announced, planned for January 1, 2027. With an existing grid connection, CUBE CONCEPTS expects 6–12 months until commissioning.

Yes – provided the control system is compliant with §19. The CUBE EfficiencyUnit maintains FCR SoC (~50 %) and automatically blocks charging operations during peak load time windows. Both revenue streams operate simultaneously without manual intervention.

Since the MiSpeL determination of October 1, 2026, EEG operation and FTM marketing can be combined through the same storage system without losing the EEG subsidy. PV sites can now combine arbitrage and EEG feed-in for the first time, without the previous either-or situation. Until September 30, 2027, the consent of the grid operator and the metering point operator is required for this.

The CUBE EfficiencyUnit records every charging process and every period relevant to the peak load time windows with timestamps. The annual proof (deadline: June 30 of the following year) can be exported directly and is archived in an audit-proof manner – no manual proof required.

Multi-Use-capable means: Hardware technically supports multiple modes. Multi-Use-optimized means: The control logic automatically prioritizes revenue channels, dynamically calculates cycle thresholds, and documents §19 compliance without manual intervention. The control logic, not the hardware, is crucial.

Yes. FTM-Multi-Use (FCR, aFRR, mFRR, Arbitrage) is completely PV-independent. 200,000–300,000 € FTM revenue potential per MW/year arises exclusively from market arbitrage and balancing energy – without any self-generation.

According to the AgNes draft (BNetzA, GBK-25-01-1#3), from 2029 onwards industrial customers will pay a capacity price on an annually ordered capacity; consumption above it costs 2 to 3.5 times the energy charge, and the peak load time windows of atypical grid usage are abolished. The CUBE EfficiencyUnit keeps grid consumption below the ordered capacity and can provide flexibility for a possible new special provision, without new hardware and without a new contract.

LCOS (Levelized Cost of Storage) is the discounted total cost per discharged MWh over the lifetime: for LFP 110 €/MWh, for ZnBr 104 €/MWh (KPMG AG, Feb. 2026). For multi-use, LCOS is the minimum benchmark per cycle: an arbitrage cycle is only worthwhile if the spread is above it. FCR, on the other hand, is mostly remunerated for availability.

The Immediate Investment Program (BGBl. 2025 I No. 161 of 18.07.2025) allows, for acquisitions from 1.7.2025 to 31.12.2027, declining-balance depreciation of up to 30 % in the first year (§7, paragraph 2 of the EStG) for all companies. It can be combined with the existing special depreciation under §7g, paragraph 5 of the EStG (up to 40 % spread over up to 5 years), limited to businesses with a previous year's profit of up to €200,000. Only the combination of both results in the often-cited 70 % first-year deduction – for medium-sized and large industrial companies above the profit threshold, only the 30 % depreciation applies. BESS qualifies as a movable fixed asset. Individual tax review recommended. More information: Immediate Investment Program (article on PV systems) →

Two levers have applied since December 23, 2025: (1) According to §11c EnWG, the construction and operation of energy storage systems are in the overriding public interest and take priority when weighing protected interests; for electricity storage systems this has applied since 2023. (2) §35, Paragraph 1, No. 11 and 12 of the Building Code (BauGB) privilege battery storage systems in outlying areas: when spatially and functionally linked to an existing renewable energy installation (No. 11), or from 4 MW at most 200 m from a substation or a power plant of 50 MW or more (No. 12). Note: Energy Sharing under §42c EnWG (since June 1, 2026) is only open to companies that are SMEs, not to large industry.

17 – Next step

Analyzing the multi-use potential – site-specific

Section 118(6) of the EnWG – Time until the due date for the investment decision (AgNes draft)
83 days
January 1st, 2027
Investment decision (draft)
August 4, 2029
Commissioning §118
17–25 k€/month
unused gross revenue potential at 1 MW

Submit your load profile. CUBE CONCEPTS calculates BTM and FTM potentials separately – based on current market data and the AgNes draft determination of 06.08.2026. Open-book modeling in three regulatory configurations, free of charge, no commitment required.

Submit load profile – free potential analysis →

Without a timely investment decision, the new fee system (AgNes draft) will apply to new storage from 2029 onwards · calculated to be €17,000–25,000 gross market revenue per month per MW

Note on content and status

As of: 09.10.2026. AgNes information based on the draft determination of 06.08.2026; the final determination is planned for the end of 2026. All regulatory information (CISAF, KUEBLL, AgNes, MiSpeL, §118 EnWG, EEG amendment 2027, Immediate Investment Program) is based on sources published at the time of writing; determinations, statutory ordinances and EU notifications may change. Tax statements are not tax advice – individual review by a tax advisor is required. Profitability figures (FTM revenues, IRR, NPV, payback) are market benchmarks or KPMG comparison calculations and not guaranteed returns. Site-specific modeling is required.