Rising redispatch costs

The rapidly rising redispatch costs highlight the bottleneck of Germany's energy transition: a lack of transmission capacity prevents the transport of green electricity from the north. This leads to billions in charges for grid fees and forces grid operators to curtail clean wind power, while fossil fuel power plants in the south fill the gaps.

The rising redispatch costs in Germany highlight the challenges in the energy sector. Despite a slight decrease in costs in 2023 compared to the previous year, the overall burden on the electricity grid and consumers remains high.

19 TWh were lost in 2023 due to grid bottlenecks

In 2023, wind turbines were more frequently shut down due to the networks not having enough capacity to carry the electricity from the north to the south. These grid bottlenecks resulted in the loss of approximately 19 terawatt-hours of electricity, which corresponds to approximately four percent of the total electricity generation in Germany. Wind farms were particularly affected by redispatching, while coal and gas power plants in the south had to generate additional electricity to meet demand.

Redispatch costs have been rising rapidly since 2020

The costs of redispatching, including feed-in management, amounted to around 2.35 billion euros in 2023, compared to 2.7 billion euros in 2022. This represents an increase of 2,345 percent compared to 2013. Analysis of data from the Federal Network Agency shows that compensation measures for congestion management are becoming increasingly necessary. Thus, the total regulatory demand in 2022 increased by 19 percent compared to 2021 to 32,772 GWh. The costs for this amounted to 4.2 billion euros in 2022, of which 2.7 billion euros were solely attributable to redispatch. Particularly between July 2021 and July 2023, the costs fluctuated significantly, ranging between 32 and 477 million euros depending on the month. Another decisive factor in 2024 will also be the elimination of the planned subsidies of 5.5 billion euros for the transmission network operators (TNOs), which was necessary as part of the budget realignment in December 2023.

Reasons for the rising redispatch costs

Various factors contribute to the rising costs, including the delay in grid expansion and the insufficient expansion of renewable energy in the south. While bottlenecks in the transmission network occur primarily in the south, more renewable electricity is produced in the north by wind power plants than is needed, which leads to additional challenges in electricity transmission. On a windy but overcast day, for example, a lot of electricity is generated in the north, while less flows in the south. Therefore, a high transmission capacity would be needed to transport the electricity from the north to the south. However, this is not yet sufficient, especially in Bavaria.

The lack of transmission capacity is also a problem for climate protection, as the power plants that are usually activated in the course of redispatching burn fossil fuels. Although feed-in priority for renewables generally applies, coal and gas power plants are usually used to stabilize the electricity grid when there is not enough renewable electricity available.

In order to prevent the electricity grid from overloading, the TSOs must therefore intervene more frequently. These processes and the so-called regular energy drive the redispatch costs sky-high. Depending on the time of day and weather conditions, the volatile electricity generation of renewable energy sources in Germany currently ranges between 3 and 55 gigawatts. In good months, this requires approximately 300 interventions, and in volatile months, up to 4,500 deviations must be compensated for.

Direct impact on the electricity price

The effects of rising redispatch costs are far-reaching. Firstly, they are included in the standardized nationwide calculations of the four German TSOs which they then pass on to the approximately 850 regional Distribution system operator pass on. From here, the costs for using the electricity grid vary considerably depending on the region and provider, and price differences of up to 300 percent with the Electricity grid charges arise. The redispatch costs are usually reflected directly in grid fee increases for private households. For energy-intensive commercial and industrial customers in the medium voltage range, who usually conclude highly individual electricity supply contracts, the increase is usually not felt until somewhat later.

Conclusion

The current challenges in the German energy sector urgently require solutions to drive forward grid expansion and reduce electricity costs at the same time. A fundamental reform of grid fees could enable a fairer distribution of costs and create incentives for a more flexible use of electricity. Measures should also be taken to increase transmission capacities and reduce the use of fossil fuel power plants. Concerted action at a political and economic level is required to tackle these challenges and successfully drive forward the energy transition.

From practice

More than 300 MWp installed: References with key figures per project

Photovoltaics and battery storage for industry and commerce: performance, power output and CO₂ savings per installation, plus feedback from our customers.

Free initial consultation

Analyze load profile — get a first assessment in 30 minutes.

CUBE CONCEPTS analyzes grid connection, load profile, and price structure — manufacturer-independent, open-book, without commitment.

More interesting articles

Wafers in the photovoltaic header

Wafers in photovoltaics

You are the heart of every solar cell, and as thin semiconductor wafers, you significantly determine the efficiency and longevity of PV modules. Learn how material purity and modern manufacturing processes optimize the conversion of sunlight into electrical energy, and what the differences are between mono- and polycrystalline wafers.

Read more "
Solar carports - aerial view

Newsletter registration