facebook

MiSpeL 2026: When does the determination apply and what does it mean for BESS projects?

MiSpeL is considered one of the most important regulatory advances for storage in Germany. In practice, it is now crucial when the new rules will come into effect and be usable.

In September 2025, in our post “MiSpeL: More Market & Opportunities for Large-Scale Storage”explains what the reform means and what options it opens up for large-scale storage. Since then, the process has evolved further – and the central question in conversations with industrial customers is now almost always: When can I expect this, and what do I need to prepare in the meantime?

This post provides a clear answer based on the current procedural status (May 2026) and derives concrete recommendations for operators of large-scale battery storage systems.

The official schedule of the Federal Network Agency

The MiSpeL determination is not a single legislative act, but a multi-stage regulatory process. The Federal Network Agency (BNetzA) carries it out based on its powers under Section 85d of the EEG 2023. Here's an overview of all the essential milestones:

MomentMilestones
February 25, 2025"Power peak law comes into effect (EEG § 19 Para. 3b and 3c)"
July 2025BNetzA opens the MiSpeL (Ref. No.: 618-25-02) designation procedure
September 18, 2025Publication of the draft determination for public consultation
October 24, 2025End of consultation period - industry associations call for H1/2026 entry into force
January 1, 2026Abolition of double grid charge burden for fed-back electricity (EnWG Amendment)
March 17, 2026Definition of mathematical rules and measurement specifications for mixed operation
June 30, 2026End of the statutory deadline for the legal finality of the MiSpeL determination
July 1, 2026Actual entry into force and start of the implementation obligation for the determination contents
January 1, 2027Start of billing via standardized, fully automated market communication

Crucial The statutory deadline runs until June 30, 2026. Industry associations such as the bne (Federal Association for the New Energy Economy) are calling for an earlier effective date in the first half of 2026 to cushion peak feed-in in the summer of 2026. Whether the BNetzA will fully exhaust the deadline is still open at this time (May 2026).

What “finality” really means here – an important distinction

Many market participants equate “legal force of the determination” with “immediately applicable.” This is a mistake that can lead to miscalculations in investment planning.

Legal force ≠ immediate applicability

Even if the BNetzA adopts the regulation by the June 30, 2026 deadline, the new options will not automatically apply directly from July 2026. In addition, the following are required:

  • EU State Aid Approval (pending, especially for the demarcation option)
  • Technical implementation by network operators and metering point operators
  • Adapting market communication processes

The full implementation obligation for all grid operators is officially planned from January 1, 2027. During a transition phase between the entry into force of the law and full operation, bilateral coordination with grid operators will be the norm, not the exception.

For BESS operators, this means: The new Accrual option (§ 19 Paragraph 3b EEG and § 21 Paragraphs 1 to 4 EnFG), the only economically relevant option for plants from 1 MWh onwards, can be used in regular operation at the earliest from the beginning of 2027 – and even then, only with timely EU approval.

Why industry associations are pushing for swift enactment

The pressure on the BNetzA comes from multiple directions – and it is justified:

  • Network stability Input tips: Without MiSpeL Co-Location BESS do not use the stored green electricity in a market-optimized way. This increases the risk of negative electricity prices and curtailment.
  • Investment Security Missing investment basis: Project developers and industrial customers hesitate with new Battery storage-Investments as long as the regulatory framework is not yet final.
  • Parallel Relief Additionally, the EnWG amendment, effective January 1, 2026, abolishes the double network charge burden for stored power fed back into the grid. This step is already legally binding and immediately improves the economic viability of large-scale storage systems.

What large-scale storage operators need to do now

The period until entry into force is not a passive waiting phase. Those who already operate a large battery storage system and want to seamlessly switch to MiSpeL operation from the outset in 2027 must act today – particularly in three areas:

Prepare measuring equipment

The demarcation option requires two smart metering systems with 15-minute intervals: one for the PV feed-in, one for grid power draw by the storage. These systems must be commissioned and installed by the responsible metering point operator – in practice, this takes several months.

2. Check direct sales structure

The prerequisite for using both new options is the direct marketing of the generated electricity. Those who still charge according to the fixed feed-in tariff must check whether and when a change makes sense. This also applies to the flat-rate option – although it is economically hardly relevant for large storage systems (from approx. 1 MWh) as it is limited to systems up to 30 kWp.

3. Don't miss Section 118, Paragraph 6 of the EnWG

Parallel to MiSpeL, there is a time-sensitive funding regulation: The Network surcharge exemption According to §118 Paragraph 6 of the EnWG, for battery storage systems put into operation before August 4, 2029, this applies for 20 years. Given a planning lead time of 6 to 12 months, project development should begin at the latest now.

What remains open – and what risks investors should be aware of

MiSpeL creates planning certainty, but not completely. Three points remain unresolved as of today (May 2026):

  • EU State Aid Approval: No specific date is known yet. Without it, the demarcation option is not applicable.
  • File attachments: How existing renewable energy facilities with retrofitted BESS (Battery Energy Storage Systems) are integrated into the new regulations has not yet been definitively clarified.
  • Network charge reform: How the AgNes Grid Fees 2029 Calculation is still pending. Questions regarding the network charge privileging of storage facilities are the subject of a separate BNetzA procedure.

For investors in large-scale storage projects, this means: MiSpeL is a necessary but not sufficient step. The overall economic calculation also depends on the outcome of the AgNes determination.

Conclusion: Preparation now, market launch 2027

MiSpeL will most likely become legally effective by June 30, 2026. Practical market operation – especially for the demarcation option, which is crucial for large-scale storage – will realistically start in early 2027. Full automation of market communication will follow from April 2027.

The window for preparing existing battery storage systems is narrow. Those who tackle the measurement technology, direct marketing structure, and project planning (including §118 EnWG) now can benefit from day one in 2027. Those who wait risk not only missed revenue potential but also bottlenecks with metering point operators and grid operators, who will be in high demand during the implementation phase.

Now is a good time for new BESS projects. The prerequisites for technology, metering points, and EMS are in place, and the window until August 2029 is still open.

Kostenloses Erstgespräch

Lastgang & Standort analysieren — in 30 Minuten zur wirtschaftlichsten Energielösung.

Wir analysieren Ihren Standort, Ihr Lastprofil und Ihre Bezugskosten herstellerunabhängig. Sie erfahren sofort, wie PV und Batteriespeicher Ihre Netzkosten senken und regulatorische Fristen (EnWG, EPBD) optimal nutzen – ohne technisches Risiko oder Eigeninvestition.

Regulatorik und Deadlines im Blick · Inkl. 250+ Simulationsvarianten · Kostenlos & ohne Commitment

More interesting articles

Electricity Price Forecast Comparison

Comparison of electricity price forecasts

The electricity market will remain extremely volatile until 2030, with price ranges between 50 and €250/MWh. Companies are best protected against this uncertainty through self-supply and battery storage, enabling them to profit from favorable generation periods and avoid expensive peaks.

Read more "
Solar carports - aerial view

Newsletter registration