linkedin

MiSpeL 2026: Festlegung tritt zum 1. Oktober in Kraft und was bedeutet das für BESS-Projekte?

MiSpeL is considered one of the most important regulatory advances for storage in Germany. In practice, it is now crucial when the new rules will come into effect and be usable.

In September 2025, in our post “MiSpeL: More Market & Opportunities for Large-Scale Storage”explains what the reform means and what options it opens up for large-scale storage. Since then, the process has evolved further – and the central question in conversations with industrial customers is now almost always: When can I expect this, and what do I need to prepare in the meantime?

This post provides a clear answer based on the current procedural status (May 2026) and derives concrete recommendations for operators of large-scale battery storage systems.

The official schedule of the Federal Network Agency

The MiSpeL determination is not a single legislative act, but a multi-stage regulatory process. The Federal Network Agency (BNetzA) carries it out based on its powers under Section 85d of the EEG 2023. Here's an overview of all the essential milestones:

MomentMilestones
February 25, 2025"Power peak law comes into effect (EEG § 19 Para. 3b and 3c)"
July 2025BNetzA opens the MiSpeL (Ref. No.: 618-25-02) designation procedure
September 18, 2025Publication of the draft determination for public consultation
October 24, 2025End of consultation period - industry associations call for H1/2026 entry into force
January 1, 2026Abolition of double grid charge burden for fed-back electricity (EnWG Amendment)
March 17, 2026Definition of mathematical rules and measurement specifications for mixed operation
June 30, 2026End of the statutory deadline for the legal finality of the MiSpeL determination
5. August 2026Veröffentlichung des Arbeitsstandes
1. Oktober 2026Actual entry into force and start of the implementation obligation for the determination contents
January 1, 2027Start of billing via standardized, fully automated market communication

Die gesetzliche Frist war bis zum 30. Juni 2026 ausgelaufen. Branchenverbände wie der bne (Bundesverband Neue Energiewirtschaft) forderten eigentlich ein früheres Inkrafttreten noch im ersten Halbjahr 2026, um Einspeisespitzen im Sommer 2026 abzufedern. Jetzt ist der 1. Oktober für das Inkrafttreten der MiSpel-Festlegung vorgesehen.

What “finality” really means here – an important distinction

Many market participants equate “legal force of the determination” with “immediately applicable.” This is a mistake that can lead to miscalculations in investment planning.

Legal force ≠ immediate applicability

Selbst wenn die Festlegung zum 1. Oktober 2026 in Kraft tritt, greifen die neuen Optionen nicht automatisch direkt ab Oktober. Zusätzlich sind erforderlich:

  • EU State Aid Approval (pending, especially for the demarcation option)
  • Technical implementation by network operators and metering point operators
  • Adapting market communication processes

The full implementation obligation for all grid operators is officially planned from January 1, 2027. During a transition phase between the entry into force of the law and full operation, bilateral coordination with grid operators will be the norm, not the exception.

For BESS operators, this means: The new Accrual option (§ 19 Paragraph 3b EEG and § 21 Paragraphs 1 to 4 EnFG), the only economically relevant option for plants from 1 MWh onwards, can be used in regular operation at the earliest from the beginning of 2027 – and even then, only with timely EU approval.

Why industry associations are pushing for swift enactment

The pressure on the BNetzA comes from multiple directions – and it is justified:

  • Network stability Input tips: Without MiSpeL Co-Location BESS do not use the stored green electricity in a market-optimized way. This increases the risk of negative electricity prices and curtailment.
  • Investment Security Missing investment basis: Project developers and industrial customers hesitate with new Battery storage-Investments as long as the regulatory framework is not yet final.
  • Parallel Relief Additionally, the EnWG amendment, effective January 1, 2026, abolishes the double network charge burden for stored power fed back into the grid. This step is already legally binding and immediately improves the economic viability of large-scale storage systems.

What large-scale storage operators need to do now

The period until entry into force is not a passive waiting phase. Those who already operate a large battery storage system and want to seamlessly switch to MiSpeL operation from the outset in 2027 must act today – particularly in three areas:

Prepare measuring equipment

The demarcation option requires two smart metering systems with 15-minute intervals: one for the PV feed-in, one for grid power draw by the storage. These systems must be commissioned and installed by the responsible metering point operator – in practice, this takes several months.

2. Check direct sales structure

The prerequisite for using both new options is the direct marketing of the generated electricity. Those who still charge according to the fixed feed-in tariff must check whether and when a change makes sense. This also applies to the flat-rate option – although it is economically hardly relevant for large storage systems (from approx. 1 MWh) as it is limited to systems up to 30 kWp.

3. Don't miss Section 118, Paragraph 6 of the EnWG

Parallel to MiSpeL, there is a time-sensitive funding regulation: The Network surcharge exemption According to §118 Paragraph 6 of the EnWG, for battery storage systems put into operation before August 4, 2029, this applies for 20 years. Given a planning lead time of 6 to 12 months, project development should begin at the latest now.

What remains open – and what risks investors should be aware of

MiSpeL creates planning certainty, but not completely. Three points remain unresolved as of today (May 2026):

  • EU state aid approval: A specific date is not yet known. Without it, the new flat-rate option for PV systems up to 30 kWp, storage systems and/or charging points as well as other consumption behind the feed-in or withdrawal point cannot be applied.
  • Network charge reform: How the AgNes Grid Fees 2029 Calculation is still pending. Questions regarding the network charge privileging of storage facilities are the subject of a separate BNetzA procedure.

For investors in large-scale storage projects, this means: MiSpeL is a necessary but not sufficient step. The overall economic calculation also depends on the outcome of the AgNes determination.

Conclusion: Preparation now, market launch 2027

MiSpeL wird mit hoher Wahrscheinlichkeit ab dem 1. Oktober 2026 rechtskräftig. Der praktische Marktbetrieb – insbesondere für die Abgrenzungsoption, die für Großspeicher entscheidend ist – startet realistischerweise Anfang 2027. Die Vollautomatisierung der Marktkommunikation folgt ab April 2027.

The window for preparing existing battery storage systems is narrow. Those who tackle the measurement technology, direct marketing structure, and project planning (including §118 EnWG) now can benefit from day one in 2027. Those who wait risk not only missed revenue potential but also bottlenecks with metering point operators and grid operators, who will be in high demand during the implementation phase.

Now is a good time for new BESS projects. The prerequisites for technology, metering points, and EMS are in place, and the window until August 2029 is still open.

Free initial consultation

Analyze load profile & location — find the most cost-effective energy solution in 30 minutes.

We analyze your location, load profile, and procurement costs independently of manufacturers. You will find out immediately how PV and battery storage systems can reduce your grid costs and make optimal use of regulatory deadlines (EnWG, EPBD) – without technical risk or capital investment.

Keep an eye on regulations and deadlines · Incl. 250+ simulation variants · Free & without commitment

More interesting articles

Whitepaper - Solar carports and PV roofs

PV roofs & solar carports for companies

Whether for fleet protection or innovative Agri-PV: Our whitepaper offers you a well-founded compendium on the potentials and financing of solar canopies. Secure your free download now and discover how to transform unused areas into lucrative power plants and optimally utilize government grants.

Read more "
reform-network-fee-rebates-header

Reform of grid fee rebates for industry planned

The planned reform transforms grid fees into control signals: Discounts will be available in the future for increased load during times of high renewable energy feed-in and throttling during scarcity. This promotes industrial flexibility, relieves the power grids, and is a central component of the new German energy strategy for integrating volatile energy sources.

Read more "
Solar carports - aerial view

Newsletter registration